- +49 8042 9176-0
- [email protected]
- Mon - Thu 08:00 am - 04:30 pm | Fri 08:00 am - 01:00 pm
2.6 FREY reserves the right to withdraw from the contract if the risk of collectability of the claim against the Buyer cannot be insured with credit insurers at the usual rates for reasons relating to the Buyer. FREY is entitled to withdraw from the contract by written declaration to be received by the Buyer either by post or fax no later than 14 days following the date of the order confirmation.
3.1. Unless otherwise agreed, the prices of FREY valid at the time of the conclusion of the contract shall apply. FREY‘s prices are quoted in EUR and EXW excluding the respectively applicable VAT and any other indirect taxes or customs duties.
3.2. The Buyer will be charged separately for packaging. The same shall apply to any customs duties, fees, taxes or any other public charges.
3.3. If the goods are shipped by FREY at the Buyer‘s request (cf. clause 6.1), the Buyer shall bear all cost of transport as well as the cost of any transport insurance requested by the Buyer.
3.4. FREY may consider an increase of the material procurement costs, wage and ancillary wage costs as well as energy cost in its prices if the delivery is delayed or postponed by more than three months due to circumstances for which the Buyer is responsible.
3.5. FREY requires the following information to be able to review whether deliveries within the territory of the European Union are exempt from VAT:
3.5.1. VAT identification number;
3.5.2. name and address of the Buyer;
3.5.3. destination; and
3.5.4. provision of all documents required to prove an intra-Community supply exempt from tax (supporting documents, acknowledgements of receipt etc.).
provision of all documents required to prove an intra-Community supply exempt from tax (supporting documents, acknowledgements of receipt etc.).
If FREY is charged with the subsequent payment of VAT due to incorrect or incomplete information provided by the Buyer, FREY is entitled to claim such amount from the Buyer. If the Buyer culpably provided incomplete or incorrect information, the Buyer shall be liable for damages vis-à-vis FREY.
3.6. Invoices shall be due for payment upon receipt. The Buyer shall be obliged to pay the purchase price within ten days.
3.7. Discounts and price reductions shall be separately agreed upon in writing.
4.1. FREY is entitled to effect partial deliveries provided that this is acceptable to the Buyer. In case of partial deliveries, FREY may request payment of their share of the total order value. FREY may require the Buyer to accept partial deliveries which are complete as such within the meaning of sentence 1.
FREY collects and processes personal data of the entrepreneur exclusively in accordance with the statutory provisions of the Federal Data Protection Act (BDSG) and the EU General Data Protection Regulation (GDPR). FREY processes and uses the data collected from the entrepreneur in the context of his order for the establishment, execution and termination of the contractual relationship with the entrepreneur, including the processing of warranty claims. FREY only passes on personal data of the entrepreneur to third parties if and insofar as this is necessary for the execution of the contract, in particular for the execution of the delivery. The legal basis for data processing is Art. 6 para. 1 lit. b GDPR. The personal data will be deleted unless statutory retention periods prevent this. To assert your rights to information, rectification, erasure, restriction or objection, please contact our data protection officer at [email protected]. You can also find a detailed description of the handling of personal data and your rights in the general data protection information sheet at https://freysysteme.de/en/privacy-policy/
1.1 These General Terms and Conditions of FREY apply exclusively to all assembly services, including monitoring and repair work, undertaken by FREY. Terms and conditions of the Contractor that deviate from or conflict with these GTCS shall not be recognised by FREY unless FREY has expressly agreed to their validity in writing. This requirement of consent also applies if FREY carries out the delivery to the entrepreneur without reservation in the knowledge of the entrepreneur’s terms and conditions. In addition, the General Terms and Conditions of Sale and Delivery of FREY shall apply.
1.2 Verbal collateral agreements have not been made. All agreements made between FREY and the entrepreneur must be in writing. This also applies in particular to legally relevant declarations and notifications to be made by the Contractor to FREY after conclusion of the contract (e.g. setting of deadlines, notification of defects, declaration of cancellation or reduction).
1.3 These GTC shall only apply to entrepreneurs, legal entities under public law and special funds under public law within the meaning of Section 310 (1) BGB.
1.4 These GTC shall also apply to all future contracts with the entrepreneur, even if FREY no longer expressly refers to them.
2.1 Orders are concluded in accordance with the conditions of the delivery order, insofar as the order includes assembly services, otherwise FREY can accept offers within two weeks of receipt. Orders placed by the entrepreneur constitute binding offers. Acceptance is effected by declaration or performance of the service.
2.2 The execution of the assembly order results exclusively from the contractually agreed specifications. FREY may make changes to the execution of the installation order at any time, insofar as these are (a) necessary to fulfil legal or official requirements, (b) do not significantly impair the quality and function of the order and (c) are reasonable for the Contractor.
3.1 Unless otherwise agreed in writing between the parties, the assembly service provided by FREY includes putting the items delivered by FREY into a mechanically and electrically operational condition.
3.2 In principle, the services of FREY do not include
3.2.1 further work to be carried out by the contractor, in particular the laying and connection of supply lines of any kind, the execution of electrical installations, assembly and commissioning of units or systems that are not part of our scope of delivery.
3.2.2 any necessary acceptance in accordance with the relevant accident prevention regulations,
unless otherwise agreed in writing.
3.3 FREY is authorised to use subcontractors.
4.1 Unless otherwise agreed, FREY’s current prices at the time of the conclusion of the contract shall apply. The prices of FREY shall be calculated according to time and effort in accordance with the assembly rates provided by FREY and valid at the time, are in Euro and do not include the applicable value added tax.
4.2 If, contrary to clause 5.1. below, FREY has to supply assembly aids, FREY shall invoice the costs incurred separately.
4.3 The agreement of a lump sum price must be made expressly. FREY calculates its lump sum offers on the following basis:
4.3.1 timely and punctual commencement of the installation;
4.3.2 normal and uninterrupted progress of the installation; and
4.3.3 assembly during normal working hours and on working days, but with the possibility, to be provided by the contractor, of also being able to provide the services assumed by FREY outside or in addition to normal working hours.
If the aforementioned bases for the price calculation do not materialise or do not exist for reasons for which the Contractor is responsible, or if the Contractor requests changes to the installation services undertaken by FREY or additional services, the resulting additional costs shall be invoiced separately to the Contractor in accordance with FREY’s installation invoice rates. This also applies to installation services requested by the Contractor outside normal working hours and outside working days.
4.4 Proof of the services rendered shall be provided in the form of work records, which FREY’s fitters shall submit to the Contractor for signature.
4.5 In order to check whether assembly services can be provided VAT-free in the European Union, FREY requires from the Contractor
4.5.1 the VAT identification number;
4.5.2 the name and address of the contractor;
4.5.3 the place of destination and
4.5.4 the provision of all documents (receipts, confirmations of receipt, etc.) required to prove a tax-exempt intra-Community supply.
In the event that FREY is charged with an additional VAT payment due to incorrect or incomplete information provided by the entrepreneur, FREY is entitled to pass this amount on to the entrepreneur. If the incorrectness or incompleteness of the information is due to a fault of the entrepreneur, he is obliged to pay damages to FREY.
4.6 Payments shall be made in accordance with the terms of the delivery order if the order includes assembly services, otherwise immediately after invoicing and without deductions.
5.1 The Contractor is obliged to co-operate insofar as this is necessary for the complete and timely execution of the contract. This refers in particular to the following services free of charge for FREY:
5.1.1 Obtaining all necessary permits and authorisations under public or private law as well as any special permits required for overtime, for example for work on Sundays and public holidays, or for special hazardous situations;
5.1.2 Provision and, if necessary, creation of an access road to the assembly site that is passable for non-terrain lorries and mobile cranes, whereby passability must also be ensured inside and outside the hall area during the entire period of assembly work;
5.1.3 Unloading of the delivered material, transport and professional storage of all delivered material at the assembly site, protected against theft, damage and weather influences;
5. 1.4 (Intermediate) transport to the assembly site with assembly and dismantling, including provision of suitable aids for intermediate transport and loading work (e.g. cranes, forklift trucks);
6.1 The Contractor shall inform FREY of the safety and accident prevention regulations applicable to the place of installation in good time before the start of installation.
6.2 The Contractor shall take the safety precautions applicable to the protection of persons and property at the place of installation. The aids to be provided by the Contractor must comply with the relevant safety regulations, in particular the accident prevention regulations.
6.3 The Contractor shall inform the fitters of FREY on site about the existing safety regulations, insofar as these are of importance for the execution of the assembly. A site or project manager appointed by the Contractor must ensure that the safety and accident prevention regulations are complied with by FREY’s fitters. The Contractor must inform FREY immediately of any infringements. In the event of serious violations, the Contractor may, in consultation with FREY, refuse the offender access to the assembly site.
6.4 In the event of emergencies or accidents, the Contractor is obliged to provide FREY’s fitters with appropriate assistance and to inform FREY immediately.
7.1 Assembly deadlines are only binding if FREY has expressly confirmed them as binding in writing. However, FREY shall endeavour to meet even non-binding assembly deadlines. An installation period shall only commence with the clarification of all technical questions necessary for the execution of the service, the timely receipt of all documents to be supplied by the Contractor or necessary authorisations as well as the timely and proper fulfilment of all other obligations of the Contractor.
7.2 A binding installation deadline shall be deemed to have been met if the object to be installed is ready for acceptance by the Contractor by the time it expires, or, in the case of a contractually agreed trial, if it is ready for testing. If additional and extension orders are placed at a later date or if additional installation services are required, the agreed installation period shall be extended accordingly.
7.3 Events of force majeure authorise FREY – even within the delay – to postpone the installation services for the duration of the hindrance. Force majeure includes all circumstances for which FREY is not responsible and which make the provision of the installation services temporarily impossible or unreasonably difficult, in particular lawful strikes or lockouts, late self-delivery for which the Contractor is not responsible, official measures, import and export bans, energy and raw material shortages and war. FREY will inform the entrepreneur about this immediately.
7.4 If the hindrance according to clause 7.3 above lasts longer than two months, the Contractor is entitled to withdraw from the contract after setting a reasonable grace period if it can prove that the outstanding fulfilment of the contract is no longer of interest to it due to the delay.
7.5 If circumstances for which the Contractor is responsible cause waiting times, exceedance of the agreed installation period and daily travelling times or multiple journeys, the resulting postponements shall not lead to a delay on the part of FREY. The Contractor shall bear the resulting additional costs according to time and effort in accordance with the applicable installation rates.
7.6 If the installation is interrupted due to circumstances for which the Contractor is responsible, the risk for the installation work already performed is transferred to the Contractor for the duration of the interruption.
7.7 If an agreed installation period is exceeded without there being a reason for this as described in clause 7.3 above, the Contractor shall grant FREY a reasonable grace period of at least 2 weeks in writing. If FREY culpably fails to comply with this grace period, the Contractor is entitled to withdraw from the contract, but not to assert claims for damages due to non-fulfilment or delay, unless Frey is liable in accordance with Clause 10.
8.1 As soon as FREY has completed the assembly and put the delivery item in a mechanically and electrically functional condition or any contractually agreed testing of the assembled delivery item has taken place, FREY shall notify the Contractor of this and request acceptance with reference to the fiction of acceptance in accordance with this Clause 8.1. FREY and the Contractor shall record the acceptance in a protocol to be signed by both parties. The Contractor shall fully inspect the installation work within a period of two weeks and either declare acceptance to FREY in writing or notify FREY in writing of the defects found. If no statement is made by the Contractor within the acceptance period, the installation work shall be deemed accepted.
8.2 If the installation proves not to be in accordance with the contract, FREY is obliged to remedy the defect at its own expense. This does not apply if and insofar as the defect is insignificant for the interests of the Contractor or is based on a circumstance for which the Contractor is responsible. If the defect is insignificant, the Customer may not refuse acceptance.
8.3 After remedying a defect, FREY shall notify the Contractor again of the completion of the installation. The Contractor shall inspect the installation work within a period of five working days. If the notified defects have been rectified and no further defects occur that prevent the use of the delivery item in whole or in part, the Contractor must declare acceptance in writing within this new acceptance period. If no declaration is made by the Contractor within this new acceptance period, the installation work shall be deemed to have been accepted.
8.4 Acceptance shall in any case be deemed to have taken place when the Contractor uses the assembled delivery item.
8.5 FREY expressly points out that acceptance by the Contractor does not automatically authorise commissioning and use. The delivery item may only be put into operation when all legal and/or official regulations to be fulfilled by the Contractor have been met.
9.1 The Contractor shall decide on the use of the items or other services supplied by FREY on its own responsibility. Unless FREY has confirmed specific properties or suitability for a contractually agreed purpose in writing, any technical advice is non-binding in any case.
9.2 If defects occur in the installation work after acceptance by FREY, the Contractor must inform FREY immediately in writing. FREY is entitled and obliged to remedy the defect. The Contractor shall grant FREY reasonable time and opportunity to determine and remedy the defect. Only in urgent cases of operational safety and to prevent disproportionately large damage, of which FREY must be informed immediately, or if FREY is in default with the elimination of the defect, the Contractor has the right to eliminate the defect itself or have it eliminated by third parties and to demand reimbursement of the necessary costs from FREY.
9.3 If FREY does not fulfil its obligation to rectify the defect and the Contractor sets FREY a reasonable grace period with the declaration that it will refuse to rectify the defect after the expiry of the grace period, the Contractor may reduce the agreed price or withdraw from the contract after the expiry of the grace period. The same shall apply if the rectification has failed or if rectification is impossible. Further claims for damages exist only in accordance with the provisions in clause 10.
9.4 FREY’s warranty does not apply to natural wear and tear, nor to damage caused after acceptance, in particular for the following reasons: unsuitable or improper use, incorrect assembly or commissioning by the contractor or third parties, damage caused by other construction works, modifications or repairs without FREY’s authorisation.
9.5 The limitation period for warranty claims is twelve months. It begins with the declaration of acceptance by the Contractor or, in the event of default of acceptance by the Contractor, with the expiry of the acceptance period.
10.1 FREY shall be liable without limitation for intent and gross negligence.
10.2 FREY shall only be liable for slight negligence if an obligation is breached, the fulfilment of which is essential for the proper execution of the order or contract (contract) and on the observance of which the entrepreneur may regularly rely. In such cases, FREY’s liability is limited to the foreseeable damage typical for such a contract.
10.3 Limitations and exclusions of liability according to this clause 10 do not apply to claims under the Product Liability Act and in the case of damages due to injury to life, body or health.
10.4 Insofar as FREY’s liability is excluded or limited, this shall apply accordingly to the personal liability of FREY’s bodies, employees, representatives and vicarious agents.
10.5 The entrepreneur’s claims for damages expire one year after the damaging event becomes known. This does not apply to claims based on intent or gross negligence, for damages due to injury to life, body or health and for claims arising from the Product Liability Act.
10.6 The Contractor shall indemnify FREY, its organs, employees, representatives and vicarious agents against any claims of third parties upon first request, which FREY and/or the aforementioned persons incur as a result of a culpable breach of duty by the Contractor. The Contractor shall reimburse FREY and the named persons for all necessary and reasonable expenses for the legal defence.
11.1 The Contractor is not entitled to assign its claims against FREY arising from this contract. This does not apply if § 354a HGB is applicable.
11.2 The Contractor shall only be entitled to set-off if its counterclaims are undisputed or have been recognised by declaratory judgement.
11.3 The same applies to rights of retention and rights to refuse performance in accordance with §§ 320, 273 BGB. The entrepreneur may only exercise such rights if they arise from the same contractual relationship. In an ongoing business relationship, each individual order is deemed to be a separate contract.
12.1 Should individual provisions or parts of these GTCS be or become invalid, the validity of all other provisions shall remain unaffected. The invalid provision shall be replaced by an agreement that comes closest to the purpose of the contract and the intention of the parties.
12.2 The contract language is German.
12.3 In case of doubt about the wording of these GTCS, the German-language text version shall apply.
12.4 The exclusive place of jurisdiction is Munich. However, FREY is also entitled to sue the entrepreneur at his general place of jurisdiction.
12.5 The law of the Federal Republic of Germany shall apply exclusively. The application of German international private law and the UN Convention on Contracts for the International Sale of Goods (UN-CISG) are excluded.